Project Details
- Client: Warrington Housing Association
- Location: Warrington
- Duration: 38 Weeks
This scheme involved the construction of a new build apartment block consisting of 4nr 1 bed 2 person apartments.
For this scheme, we undertook a rationalisation of the original planning design which solved buildability issues and reduced future maintenance costs.
This scheme is Secure By Design.
Our works involved;
Deep strip foundation
Cavity wall construction
Drainage connections
Beam and block ground floor
Concrete plank first floor
Concrete staircases
Traditional truss roof with large format tile
Full internal fit out, kitchens, bathrooms
Statutory service connections
Full M&E packages.